Union Pacific RR Diesel Shop

I am not sure why I haven't posted any photos of our newest railroad project. This is a 240,000 sq. ft project. Scope of work- Remove the existing rock ballast, remove the EPDM membrane down to the existing insulation. 1/4" densdeck will then be installed (Mechanically) over the insulation. This is a cold process project- base and cap sheet will be installed using cold process adhesive. This project was started late April and will hopefully be completed mid fall... stay tuned!!!