PROGRESS IN MANSFIELD, AR

Here is some updated photos of our progress in Mansfield, AR at the Youth Center. As you can see from the photos- The first building (Girls Dorm) All that we are waiting to complete this roof system is the aluminum coating. The existing roof system was completely removed down to the metal decking. Tapered insulation was installed then base sheet- mid ply sheet- then cap sheet.
Below the Girls dorm photos you can see the progress with the boys cabins. When i published the first photos of the boys cabins, we were informed to do a recover over the existing roofing system. After further investigating we gathered the roof systems would have to be removed down to the wood decking. The very last picture shows the base sheet over the insulation. This is not the finished product. Stay tuned!